Decision details
To Appoint Mace Ltd through a professional services contract to complete RIBA stages 3+, 5,6 for Maylord Orchards development project
Decision Maker: Corporate Director – Economy & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The proposed £3.5m redevelopment of
Maylord Orchards to create a new library and learning resource
centre is a key project in the Hereford Town Investment Plan. The
project will establish a modern library service and Learning
Resource Centre at the heart of the city, re-purposing a key area
of Hereford in creating new reasons for people to visit and spend
time and money across the centre as a whole. The Learning Resource
Centre will provide facilities to enable local people to access the
support they need to develop their skills, and access new
employment opportunities such as the council’s Adults and
Community Learning Service.
Following the decline in retail, accelerated through Covid 19, all
towns and cities need to consider how the will regenerate and
re-purpose creating new opportunities for trade, employment, living
and studying. In creating a revitalised and vibrant city centre, a
key focus of the Hereford Town Investment Plan is developing a
refocused mixed use offer focused on learning and culture. The new
library and Learning Resource Centre is a key part of this
strategy. Two other complimentary proposed projects that may also
be located in Maylord Orchards will further enhance the cultural
and educational offer, creating a local hub (being led by
Powerhouse and Rural Media separately).
In order to meet the required Stronger Towns Funding deadlines and
to keep the project progressing a range of technical support is
required. To date the council has commissioned Mace Ltd to lead a
design team through RIBA Stages 2, and 3 Further technical works
are required to finalise the design, seek planning approval, to
procure contractors and implement the project.
Subject to this decision, the council intends to procure in
accordance with the Contract Procedure Rules a specialist Project
Management and design team to lead the phased development of the
project including the completion of RIBA stage 2, planning
application stage (RIBA stage 3), procurement of a contractor (RIBA
stage 4) and the implementation and handover of the building (RIBA
Stages 5/6) on a call off basis.
Contact: Ross Cook, Corporate Director - Economy and Environment Email: ross.cook@herefordshire.gov.uk.
Publication date: 11/10/2022
Date of decision: 11/10/2022