Title | Date Created | Due Date | Decision Makers | Issue Status |
---|
The construction and management of Integrated Wetlands as tertiary treatments for waste water treatment works to reduce phosphate levels within the River Lugg catchment area | 20/04/2020 | 10 August 2020 | Cabinet member Infrastructure and transport | Recommendations Approved |
To approve expenditure up to the value of £65,500 to award professional services contracts and to complete feasibility work to progress the Integrated Wetlands project | 17/02/2021 | 16 December 2020 | Director of Economy and Place (Historic) | Recommendations Approved |
To approve the provision of technical advice by the Wye and Usk Foundation on phosphate reduction in the Lugg catchment | 21/02/2021 | 19 February 2021 | Assistant Director for Regulatory, Environment and Waste Services (Historic) | Recommendations Approved |
Appointment of consultants to develop an Interim Phosphate Delivery Plan following the completion of a procurement process | 27/05/2021 | 14 October 2020 | Assistant Director for Regulatory, Environment and Waste Services (Historic) | Recommendations Approved |
Approve expenditure up to £148,000 for survey works and professional fees necessary to progress proposed integrated wetland sites | 18/06/2021 | 17 June 2021 | Assistant Director for Regulatory, Environment and Waste Services (Historic) | Recommendations Approved |
To approve expenditure up to £165,150 for the detailed design, planning and construction oversight for 3 wetland sites, and to enter into a contract with the Wye and Usk Foundation | 14/12/2021 | 14 December 2021 | Service Director – Environment , Highways, & Waste | Recommendations Approved |
Approval for the development of the phosphate credit framework by Ricardo-AEA Ltd for £22,739 | 01/02/2022 | 27 January 2022 | Service Director – Environment , Highways, & Waste | Recommendations Approved |
To acquire land and associated access/easement rights to develop a phosphorous-reducing wetland | 09/02/2022 | 31 January 2022 | Service Director – Environment , Highways, & Waste | Recommendations Approved |
To approve expenditure up to £495,000 for construction of an integrated wetland scheme on land at Luston and to enter into a contract with JN Bentley Ltd | 16/02/2022 | 1 February 2022 | Service Director – Environment , Highways, & Waste | Recommendations Approved |
To approve expenditure up to £75,000 for the design and construction of drainage apparatus at Luston waste water treatment works | 04/03/2022 | 4 March 2022 | Service Director – Environment , Highways, & Waste | Recommendations Approved |
Approval for the development of the phosphate credit framework by Ricardo-AEA Ltd for £22,739 | 18/03/2022 | 27 January 2022 | Service Director – Environment , Highways, & Waste | Recommendations Approved |
Acquire land and associated access rights at Titley in order to develop a phosphorous-reducing wetland site | 01/04/2022 | 25 March 2022 | Service Director – Environment , Highways, & Waste | Recommendations Approved |