To Increase the contract value to complete Electricity Installation to Plot C1A and C1B
The installation of electricity to Plot C1A
and C1B forms an essential part of preparing the land for sale and
development.
Plot C1B has been sold to an end occupier. They are well advanced
with their building construction and hence will be requiring their
connection in 8-10 weeks. However the substation connection for the
designed scheme is no longer available, so we need to install an
alternative scheme to supply power to Plot C1B. An alternative
substation and route has been found. This does require additional
work from Rock Power Connections Limited to deliver, notably a new
connection across the Straight Mile. Hereford Enterprise
Zone’s Utility Consultants (SMS PLC) have confirmed that the
proposed route is acceptable and the costs are valid and
reasonable.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 17/11/2022
Decision due: 10 November 2022 by Corporate Director – Economy & Environment
Contact: Mark Pearce, Programme Director, Places and Communities Email: mark@skylonpark.co.uk Tel: 01432383521.