Issue details
Whitney on Wye Flood Damage Repairs – Contract Award
Following the decision by Cabinet on 23 July,
2020, the subsequent decision taken by the Council on the 4th
August 2020, the works to repair all remaining sites were to be
commissioned and delivered.
Consequently the Director Of Economy and Place took the decision on
the 22 September 2020 that all remaining elements of the Fownhope
work be delivered through the Public Realm Contract. The Whitney on
Wye scheme be delivered as a Design and Build Commission. The
various flood damaged sites be delivered through a framework
commission.
The Fownhope works have been delivered, the framework of flood
damaged sites is being delivered. The Whitney scheme went to tender
However no returns have been received.
2 July 2021 the Director for Economy and Place took the decision to
Whitney on Wye Scheme is delivered through the Public Realm
Services Contract with the build element delivered through an open
market contract which will follow once the design is
complete.
A council compliant procurement exercise has been completed, this
decision is to award the contract.
The tender price for the works is £187,100.94
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 31/05/2022
Decision due: 20 May 2022 by Corporate Director – Economy & Environment
Contact: Ross Cook, Corporate Director - Economy and Environment Email: ross.cook@herefordshire.gov.uk.
Decisions
- 31/05/2022 - Whitney on Wye Flood Damage Repairs – Contract Award