Issue details

Authority to approve spend on Hereford City Centre Improvement project

1) To enable the Delivery Director to make decisions around daily occurrences relating to contract Early Warning works and compensation events.
2) To significantly reduce the risk of project delay due to the council’s internal procedures relating to having the ability to spend the identified budget lines relating to the project.
3) To enable the Delivery Director to issue instructions in a timely manner around agreed risks that require financial mitigation.
4) To reduce the number of Record of Officer decisions required to enable spend which is having a negative impact on time and resources within the council.
5) The decision as listed above set out the total budgets for the individual elements of the HCCI project. The Delivery Director will only be authorised to spend within the element budgets.
6) Any changes to the agreed total budget for each element will remain delegated to the Director.

Description of project cost - Total Cost including VAT if applicable
High Existing Enhancements - £572,407.00
High Town Area Minor Works - £211,642.00
Market and event infrastructure - £30,500.00
CCTV - £60,500.00
Façade improvement grants/Business Grants - £500,000.00
Cathedral & River Wye Quarter Design - £340,000.00
St Owen St Cycle Contraflow - £700,000.00
Widemarsh St kerb Improvements - £715,000.00
Cathedral & River Wye Quarter Planters - £262,500.00
City Link Road Planters - £570,191.00
City Greening - £362,000.00
City Trees - £320,000.00
City Green Cycle Shelters - £30,000.00
Public Art/Installations - £243,000.00
Hostile Vehicle Movement - £500,000.00
HCCI Project Management Costs - £582,260.00

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 14/03/2022

Decision due: 14 March 2022 by Corporate Director – Economy & Environment

Contact: Ross Cook, Corporate Director - Economy and Environment Email: ross.cook@herefordshire.gov.uk.