Issue details
North Magazine Earthworks / Plot Raising (Contract Variation)
The additional works are an extension of
existing activities contained within the initial tender brief (i.e.
– purchase of material; levelling; compaction). The use of a
separate contractor would be highly impractical and inevitably
incur additional/duplicate preliminaries, mobilisation and site set
up costs. There would also be additional health and safety /
project management implications to consider, in attempting to
manage / coordinate two contractors within a limited working
space.
The opportunity was advertised as an open procurement exercise via
pro-contract for a period of three of 3 weeks. Of the responses
received, Owen Pell Ltd scored highest against both cost and
quality
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 03/12/2021
Decision due: 3 December 2021 by Director of Economy and Place (Historic)
Contact: Neil Taylor, Interim director of economy and place Email: Neil.Taylor@herefordshire.gov.uk Tel: 01432 260921.