North Magazine Earthworks / Plot Raising (Contract Variation)

The additional works are an extension of existing activities contained within the initial tender brief (i.e. – purchase of material; levelling; compaction). The use of a separate contractor would be highly impractical and inevitably incur additional/duplicate preliminaries, mobilisation and site set up costs. There would also be additional health and safety / project management implications to consider, in attempting to manage / coordinate two contractors within a limited working space.
The opportunity was advertised as an open procurement exercise via pro-contract for a period of three of 3 weeks. Of the responses received, Owen Pell Ltd scored highest against both cost and quality

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 03/12/2021

Decision due: 3 December 2021 by Director of Economy and Place (Historic)

Contact: Neil Taylor, Interim director of economy and place Email: Neil.Taylor@herefordshire.gov.uk Tel: 01432 260921.

Decisions