Issue details
Revision of the 2021/22 - 2022/23 Schools Capital Maintenance Planned
Revise the programme list of planned schemes,
which was originally
approved in the Cabinet Report of 17th December 2020. This is due
to
Council awarding Professional Consultancy Services to manage
delivery of
Herefordshire Council’s School Building Maintenance programme
and
receiving a high number of emergency works schemes.
To remove the following schemes, an estimated total of
£265,000, from the two
year programme:
• Garway Fire Alarm
• Michaelchurch Escley Fire Alarm
• Aylestone Distribution Boards
• Ledbury Heating
• Shobdon Distribution Boards
• Shobdon Ventilation
To re-profile the following schemes from 2022/23 to 2021/22:
• Almeley Ventilation
• Aylestone Emergency Lighting
• Garway Distribution Boards
• Ledbury Distribution Boards
To defer the following schemes from 2021/22 to 2022/23
• Aylestone Ventilation
To remove the following schemes due to the scheme no longer
required:
• Orleton Mobiles
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 27/05/2021
Decision due: 27 May 2021 by Assistant Director Education, Development and Skills (Historic)
Contact: Ceri Morgan, Education Strategic Projects Email: ceri.morgan@herefordshire.gov.uk.
Decisions