Issue details

Electricity Installation to Plot C1A and C1B

To award a contract to Rock Power Connections Limited for the installation of electricity to Plots C1A and C1B. The quoted cost for delivery of the works is £67,016. An additional £15,000 contingency needs to be included based on the risk analysis carried out by SMS plc (Enterprise Zone Utility Consultants). The total amount required to implement this decision is therefore £82,016. This additional contingency will cover any potential changes or modifications to the design and methodology.

This will be funded £53,612.80 using LEP funds with the remaining £13,403.20 (plus £15,000 contingency) coming from Phase 5 Enterprise Zone funds.

Decision type: Non-key

Decision status: Recommendations Approved

Notice of proposed decision first published: 29/03/2021

Decision due: 29 March 2021 by Director of Economy and Place (Historic)

Contact: Neil Batt, Enterprise Zone Capital Programme Manager Email: Neil.Batt@herefordshire.gov.uk Tel: 01432 383694.