Issue details
Variation to public realm annual plan 20/21 – Pothole & Challenge Fund - Structures
On 17 September 2020 the Director for Economy
and Place under the delegation from the Council of 6 August 2020
confirmed the addition of £7.674m pothole and challenge fund
works to he delivered through the public realm annual plan
2020/2021 as follows:
Carriageway Works
£ 2,604,000
Structures and Stability
£ 3,160, 000
Footways & Cycleway
£ 400,000
Countywide Drainage Improvements
£ 760,000
Signal, Roadmaking,
£ 750,000
Signs & Safety Barriers
Total
£ 7,674,000
That record of officer decision can be seen on the councils website
by following the link below
http://councillors.herefordshire.gov.uk/ieDecisionDetails.aspx?ID=7181
The Structures works element was allocated as follows:
Structures and Stability
Bridges
£ 3,160, 000
B4224 Mordiford Bridge Parapet
£250,000
U65606 Paunton Rock Armour
£200,000
C1011 Kinsham deck replacement Phase2
£600,000
C1001 Buckton deck replacement Phase2
£600,000
repairs to C1072 Kington Bridge Phase 2
£200,000
Repairs to B4214 Instone
£25,000
Repairs to A438 Letton
£35,000
Repairs A44 Eaton Bridge
£25,000
Saddling designs
£105,000
Red Lion B4352
£200,000
Hunderton River Bridge Phase 2 £75,000
U91416 Hunton Bridge/road £200,000
Retaining Wall Strategy development £60,000
Carriageway above bridge decks
£370,000.00
Roads at Risk
A4113 Leintwardine
£150,000.00
Various other sites
£10,000.00
Trereece
£5,000.00
Bridge Kits for the PROW network £50,000.00
This record of officer decision alters the allocation of the spend
on structures works set out above, and replaces it with drainage
and surfacing works set out below. This is primarily due to the
inability to undertake these structural works during environmental
embargos that restrict permissible access to these schemes. These
embargos will be in place until early March, thus not allowing
enough time to mobilise and effectively deliver all works before
the end of this financial year.
These structures schemes will be considered for next year’s
annual plan, when access is permissible and the drainage and
surfacing works will replace these structural works. The drainage
and surfacing are high priority schemes which would be considered
for delivery as part of next year’s annual plan.
The overall spend on the Pothole and challenge fund works is
unchanged.
Elements of the structures works budget to be changed are as
follows:
Scheme Original budget New Budget Budget to be re-allocated
B4224 Mordiford Bridge Parapet 250,000 £50,000 200,000
C1011 Kinsham deck replacement Phase 2 £600.00 £575,000
£25,000
C1001 Buckton deck replacement Phase 2 £600,000
£575,000 £25,000
Red Lion B4352 £200,000 £50,000 £150,000
U91416 Hunton Bridge/road £200,000 £0
£200,000
Total £600,000
Thus releasing £600K of budget for re-allocation.
This £600K funding will be re-allocated to drainage and
surfacing works as follows:-
Drainage works
A4103 70 - 80 metre run of kerbs to direct water
£10,000
Norton Cannon - Drainage channel works £10,000
Walkers Green Marden System Reinstatement £10,000
A44 Linton Lane – blockage £20,000
Hinton Villa £5,000
Rotary Ditcher & Tractor – plant investment
£125,000
Total £180,000
Surfacing Works
A44 C1081 to Beech Tree Cottage £126,000
B4214 Bishops Frome to Munderfield Stocks £163,000
B4229 A4137 to C1258 Goodrich £107,000
A417 Burley Gate to Rowleigh Phase 1 £24,000
Total £420,000
All works under the Pothole and Challenge fund 20/21 capital
project will be delivered within the grant allocation of
£7.674m
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 04/11/2020
Decision due: 3 November 2020 by Acting Assistant Director for Highways and Transport
Contact: John Manterfield, Commercial and Contract Manager Email: John.Manterfield@herefordshire.gov.uk.