Issue - decisions
Hereford Western Bypass Phase One Land Acquisition CPO
18/12/2025 - Hereford Western Bypass Phase One Land Acquisition CPO
To agree to resolve that the Council
a) note the draft Statement of Reasons (at Appendix 1);
b) makes The County of Herefordshire District Council (Hereford Western Bypass – Phase One) Compulsory Purchase Order 2026 (CPO) pursuant to sections 239, 240, 246, 250 and 260 of the Highways Act 1980 and the Acquisition of Land Act 1981 for the acquisition of all interests (both residential and commercial), and any other interests as may arise, which are not already owned by the Council and new rights within the areas shown edged red and shaded pink and blue on the plans attached at Appendix 2
c) note The County of Herefordshire District Council (South Wye Transport Package – A4194 Southern Link Road) (Classified Road) (Side Roads Order) Order 2018 (2018 SRO) attached at Appendix 3 which was confirmed by the Secretary of State in March 2019.
d) Delegate authority to the Corporate Director for Economy and Environment to
a. make The County of Herefordshire District Council (Hereford Western Bypass – Phase One) Side Road Order 2026 (SRO) (if required) under Section 14 and 125 of The Highways Act 1980 and all other purposes necessary to
i) Improve the lengths of highway referred to in the SRO and the corresponding plan
ii) Stop up each length of the highway as referred to the SRO and the corresponding plan
iii) Construct a new highway along each route as referred to in the SRO and the corresponding plan;
iv) Stop up each private means of access to premises as referred to in the SRO and the corresponding plan;
v) Provide new means of access to premises as referred to in the SRO and the corresponding plan.
which will be as per the plan appended to the 2018 SRO (subject to any amendments to the said plan the Corporate Director for Economy and Environment shall determine as being necessary if the SRO is required);
b. to make such minor or technical amendments to the CPO and or SRO (together “the Orders”) and associated plans as the Corporate Director for Economy and Environment shall determine;
c. take all necessary and ancillary steps, including preparing and finalising all necessary documentation (including the Orders and supporting statements of reasons), the submission of the Orders to the Secretary of State for confirmation, publication and service of all statutory notices and the presentation of the Council’s case at any public inquiry to secure the confirmation of the CPO and SRO by the Secretary of State;
d. acquire all interests in land within the areas of the CPO either compulsorily or by agreement;
e. deal with objections to the Orders including agreeing terms for the withdrawal of objections in order to secure the delivery of Phase One of the Hereford Western Bypass Scheme;
f. negotiate and enter into agreements or undertakings with persons with any interest in the land affected by or relating to the Orders;
g. remove from the CPO any plot (or interest therein) no longer required to be acquired compulsorily and to amend the interests scheduled in the CPO (if so advised) and to alter the nature of the proposed acquisition from an acquisition of existing property interests to an acquisition of new rights ;
h. make any minor amendments as are considered necessary to the Orders arising as a result of negotiations with affected persons or further design work to enable the delivery of Phase One of the Hereford Western Bypass Scheme
i. make any amendments to the Statement of Reasons a draft version of which is annexed at Appendix 1 to this report as are considered necessary prior to its submission to the Secretary of State;
j. confirm the CPO if granted power to do so by the Secretary of State;
k. to implement the CPO, SRO and 2018 SRO, including the acquisition of all necessary land and interests and new rights and to take all steps to secure the settlement of compensation arising from the implementation of the Orders including referral to the Upper Tribunal Lands Chamber.
l. to pay such compensation and to carry out any other additional steps needed for the implementation of the CPO, SRO and 2018 SRO and make any other operational decisions to implement these recommendations;