Issue - decisions
Decision to approve an Early Works Instruction in respect of Peterchurch Primary School project for early procurement and site mobilisation works
19/06/2025 - Decision to approve an Early Works Instruction in respect of Peterchurch Primary School project for early procurement and site mobilisation works
Decision to approve an Early Works Instruction
under the Pre-Services
Construction Agreement in respect of the Peterchurch Primary
School
project for enabling works to be instructed.
The Early Works Instruction 2 will instruct early procurement and
site
mobilisation works at a cost of £168,083.27 due to a long
lead in time and
to ensure there is not a delay to programme, this is within the
budgets set
aside for these elements of the project.