Issue - decisions
Approval of contingency budget to finance “change events” that will mitigate risks occurring in the Shell Store project
12/11/2019 - Approval of contingency budget to finance “change events” that will mitigate risks occurring in the Shell Store project
Approve the use of is £27,343.44 from
the Shell Store project contingency approved budget on repairs to
the concrete floor slab £25,639.56, and repairs to the steel
frame £1,703.88 specialist explosives testing, and
remediation and validation surveys and lead testing