Enterprise Zone Capital Interventions Phase 5

08/08/2019 - Enterprise Zone Capital Interventions Phase 5

That:

 

(a)       £5.231m from the enterprise zone capital programme provision be allocated to the following infrastructure interventions at the Hereford enterprise zone:

Infrastructure Interventions

Allocation  (£000’s)

Spoil Heap removal, movement and ground raising Phase 2 delivery.

2,100

Utilities commissioning, installation and movement – gas, electricity, foul and potable water, SUD’s, broadband.

600

Plot specific works including investigation, preparation and readiness for sale and construction.

750

Access improvements, roads, cycleways, sustainable transport infrastructure.

1,300

Estate wide management, maintenance and improvement works including signage, landscape and drainage.

481

TOTAL

5,231

 

(b)      the acting Director for Economy and Place be authorised to implement the above interventions, including the procurement and commissioning of works packages of over £500k;

 

(c)       the total capital allocation of £16m for the EZ development be funded from existing capital receipts.