Agenda item

DCNC2005/3164/F - PROPOSED 2 NO THREE BEDROOM DWELLINGS AT LAND NW OF STONEHOUSE, BODENHAM, HEREFORD HR1 3HS. For: Mr S Davies at same address

Ward: Hampton Court

Minutes:

In accordance with the criteria for public speaking, Mr. Powell (objector) spoke against the application.

 

Councillor KG Grumbley, the Local Ward Member, had a number of concerns about the application, feeling that the proposal would be an overdevelopment of the site.  He also felt that there were potential problems with drainage because there was no mains sewer and mains water.  It was crucial that adequate measures were put in place to deal with surface water drainage because disposal of surface water into the ditch near to the proposed property would add to flooding of the C1125 which was already a significant problem in adverse weather conditions.  He felt that it was essential for the Environment Agency and the Transportation Manager to be satisfied with the arrangements prior to the scheme commencing and the Sub Committee concurred with his views.

 

RESOLVED THAT

 

planning permission be granted subject to the following conditions and the prior agreement of the Environment Agency, Welsh Water Authority and the Transportation Manager about sewer and drainage arrangements:

 

1 -     A01 (Time limit for commencement (full permission) )

 

         Reason: Required to be imposed by Section 91 of the Town and Country Planning Act 1990.

 

2 -     A06 (Development in accordance with approved plans )

 

         Reason: To ensure adherence to the approved plans in the interests of a satisfactory form of development.

 

3 -     B01 (Samples of external materials (general) )

 

         Reason: To ensure the external materials harmonise with the existing building.

 

4 -     F48 (Details of slab levels )

 

         Reason: In order to define the permission and ensure that the development is of a scale and height appropriate to the site.

 

5 -     G09 (Retention of trees/hedgerows )

 

         Reason: To safeguard the amenity of the area.

 

6 -     H03 (Visibility splays )  (2m x 33m)  (Plot 2)

         Before any other works hereby approved are commenced, visibility splays for Plot 2  shall be provided from a point 0.6 metres above ground level at the centre of the access to 2 metres back from the nearside edge of the adjoining carriageway (measured perpendicularly) for a distance of 33 metres in each direction along the nearside edge of the adjoining carriageway.  Nothing shall be planted, erected and/or allowed to grow on the triangular area of land so formed which would obstruct the visibility described above.

 

         Reason: In the interests of highway safety.

 

7 -     H03 (Visibility splays)  (2m x 33m L, 2m x 20m R) (Plot 1)

 

         Reason: In the interests of highway safety.

 

8 -     H05 (Access gates )  (5m)

 

         Reason: In the interests of highway safety.

 

9 -     H09 (Driveway gradient )

 

         Reason: In the interests of highway safety.

 

10 -   H13 (Access, turning area and parking )

 

         Reason: In the interests of highway safety and to ensure the free flow of traffic using the adjoining highway.

 

11 -   F16 – Restriction of hours during construction

 

         Reason:  To protect the amenity of local residents.

 

12 -   F18 – Scheme of foul drainage disposal

 

         Reason:  In order to ensure that satisfactory drainage arrangements are provided.

 

Informatives:

 

1 - N15 - Reason(s) for the Grant of PP/LBC/CAC

2 - HN01 - Mud on highway

3 - HN05 - Works within the highway

4 - HN10 - No drainage to discharge to highway

Supporting documents: