Agenda item

DCSE2005/3208/O - LAND OFF TANYARD LANE, ROSS-ON-WYE, HEREFORDSHIRE.

Site for residential and associated development, including linear park and site access.

Minutes:

It was reported that the following updates had been received:-

 

Welsh Water state that they have been provided with additional information which demonstrated that the proposals would not result in an increase in flows to the public sewerage system.  They ask that conditions and advisory notes be incorporated within the planning consent  relating  to drainage of the site.

 

The applicant’s agent has submitted a copy of a letter e-mailed to all Members of the Committee, which included a Technical Briefing Note on Drainage Issues.

 

No changes were proposed to the recommendation.  Paragraph 6.4 of the report should be corrected: the capacity available for foul effluent would allow for development of both the Tanyard Lane site and the laundry site.

 

In accordance with the criteria for public speaking, Mr Sacket the agent acting for the applicant spoke in support of his application.

 

 

Several concerns were expressed by local ward Councillors regarding foul and surface water drainage of the site and the proposals for the new roundabout on the Ross Relief road which would provide access to the site. The Principal Planning Officer said that the drainage issues would be controlled by conditions and he outlined what the disposal arrangements would be.  The application was an outline one and that the details would be incorporated within the planning obligation to be prepared by the officers which would address the concerns raised by Members.  He also said that the proposed roundabout would be the subject of a separate application.  The Southern Team Leader reminded Members that the site was identified for development within the Herefordshire Unitary Development Plan which would shortly be adopted.  He said that the outline permission needed to be granted in order that a detailed application could be dealt with.  Members asked a number of questions about the proposals.

 

 

RESOLVED

 

that subject to the completion of noise surveys and an indication of appropriate mitigation:

 

            1)         the Legal Practice Manager be authorised to complete a planning obligation agreement under Section 106 of the Town and Country Planning Act 1990 regarding contributions towards education, open space, adoption of open space, affordable housing and highway works.

 

            2)         upon completion of the aforementioned planning obligation that the officers named in the Scheme of Delegation to officers be authorised to issue planning permission subject to the following conditions and any additional conditions considered necessary by officers:

 

1.      A02 (Time limit for submission of reserved matters (outline permission))

 

         Reason: Required to be imposed by Section 92 of the Town and Country Planning Act 1990.

 

2.      A03 (Time limit for commencement (outline permission))

 

         Reason: Required to be imposed by Section 92 of the Town and Country Planning Act 1990.

 

3.      A04 (Approval of reserved matters)

 

         Reason: To enable the local planning authority to exercise proper control over these aspects of the development.

 

4.      A05 (Plans and particulars of reserved matters)

 

         Reason: Required to be imposed by Section 92 of the Town and Country Planning Act 1990.

 

5.      D01 (Site investigation - archaeology)

 

         Reason: To ensure the archaeological interest of the site is recorded.

 

6.      F13 (Scheme to protect new dwellings from road noise)

 

         Reason: To protect the residential amenities of the future occupiers of the properties.

 

7.      H11 (Parking - estate development (more than one house))

 

         Reason: In the interests of highway safety and to ensure the free flow of traffic using the adjoining highway.

 

8.      H27 (Parking for site operatives)

 

         Reason: To prevent indiscriminate parking in the interests of highway safety.

 

9.      H29 (Secure cycle parking provision)

 

         Reason: To ensure that there is adequate provision for secure cycle accommodation within the application site, encouraging alternative modes of transport in accordance with both local and national planning policy.

 

10.    Prior to the occupation of any of the (specify) hereby permitted a management plan, to include proposals for the long term design objectives, management responsibilities and maintenance schedules in perpetuity, for the areas of open space and play area(s) but excluding private domestic gardens, shall be submitted to and be approved in writing by the local planning authority.  The management plan shall be carried out as approved. 

 

         Reason:  In order to ensure that the use and maintenance in perpetuity of the open space and play area(s) is assured.

 

11.    F16 (Restriction of hours during construction)

 

         Reason: To protect the amenity of local residents.

 

12.    F41 (No burning of materials/substances during construction phase)

       

         Reason: To safeguard residential amenity and prevent pollution.

 

13.    W01 (Foul/surface water drainage)

 

         Reason: To protect the integrity of the public sewerage system.

 

14.    W02 (No surface water to connect to public system)

 

         Reason: To prevent hydraulic overloading of the public sewerage system, to protect the health and safety of existing residents and ensure no detriment to the environment.

 

15.    W03 (No drainage run-off to public system)

 

         Reason: To prevent hydraulic overload of the public sewerage system and pollution of the environment.

 

16.    Prior to the commencement of the development a detailed programme and method statement to include a timetable for the implementation and completion of the development shall be submitted to and approved in writing by the local planning authority.  The development shall be progressed in accordance with the approved details.

 

         Reason:  In order to ensure that the development is progressed to completion.

 

17.    No development within the application area shall be occupied unless the mitigation proposals as shown on Drawing No. 50319/003 rev C has been completed to the satisfaction of the local planning authority after consultation with the Highways Agency.

 

         Reason:  To ensure that the A40 Trunk Road continues to serve its purpose as part of a national system of routes for through traffic in accordance with Section 10(2) of the Highways Act 1980 by minimising disruption on the trunk road resulting from traffic entering and emerging from the application site and in the interests of road safety.

 

Informative(s):

 

1.      N19 - Avoidance of doubt

 

2.      N15 - Reason(s) for the Grant of Planning Permission

Supporting documents: