The strategic finance manager presented the findings of the triennial review of the Whitecross PFI contract, it was noted that the Council was adding an additional £100k to the annual cost of the contract due to inflationary pressures.

 

In response to a query the SFM confirmed the contract ends in 2031.

 

Resolved:

That:

a) The council’s planned increase of £100,000 for 2024/25 to bring the annual base budget to £1,128,350 per annum was noted

b) The annual contribution be reviewed taking account of the then inflation rate at the next triennial review in Autumn 2026;

c) The report of the next triennial review be received by Schools Forum in January 2027