Decision details
Priority Flood Works- Budget Allocation
Decision Maker: Corporate Director – Economy & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
Cabinet recommended to council the
£4.027m (priority flood repair works) be added to the Capital
Programme, this was approved 23 July 2020.
A further decision was taken 8 October 2021 to reallocate the
budgets as below.
https://councillors.herefordshire.gov.uk/mgIssueHistoryHome.aspx?IId=50038920&Opt=0
The Fownhope Flood Repair works are complete but is closing out in
regards to finance, the Whitney Scheme is now complete. The
allocated budget was more than the actual cost, this decision will
utilise the unspent budget.
The contingency spend is available to support the various sites,
the additional schemes have been developed and delivery is expected
in March, to provide improved benefit to the network.
A contingency will remain to cover claims resulting from direct
impact of the flood works.
Contact: Ross Cook, Corporate Director - Economy and Environment Email: ross.cook@herefordshire.gov.uk.
Publication date: 16/03/2023
Date of decision: 15/03/2023