Decision to spend from the Property Services Estates Capital Works Programme to upgrade the electrical distribution boards at Ross-0n-Wye Library

Decision Maker: Acting Head of Property (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The latest condition survey called for replacement of the end of life main electrical distribution boards.

Melcon Hereford Ltd have been identified as the bidder representing
best value for money following a competitive tender and assessment
process in accordance with Council procurement procedures. Quotations
were invited from three prospective companies and two returned a
valid quotation for consideration.

The work to be awarded to Melcon Hereford Ltd at a cost of £11,055
out of the £25,000 capital budget.

There is also a boost to the local economy as Melcon Hereford Ltd are a local contractor.

Contact: Philip Huggett, Special projects officer Email: philip.huggett@herefordshire.gov.uk Tel: 01432 260018.

Publication date: 13/12/2021

Date of decision: 08/12/2021