Decision details
Construction of North Magazine Haul Road, Hereford Enterprise Zone
Decision Maker: Director of Economy and Place (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The construction of the haul road will provide
NMITE with the required access to undertake construction activities
in relation to the new educational campus over the construction
period, whilst allowing the planned infrastructure for the North
Magazine to be developed.
Three quotations have been secured for carrying out the work via
the pro contract system. The Council’s contract procedure
rules have been followed with support from the Commercial team.
Owen Pell Limited scored highest in the evaluation exercise.
The tender is based on a 6 week delivery period.
Contact: Neil Batt, Enterprise Zone Capital Programme Manager Email: Neil.Batt@herefordshire.gov.uk Tel: 01432 383694.
Publication date: 17/11/2020
Date of decision: 17/11/2020