To approve the additional expenditure of up to £5k for planned maintenance switchgear replacement (total cost £21k) at Trinity Primary School

Decision Maker: Director of Children and Families (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Approval of the additional costs associated with the switchgear replacement planned maintenance works at Trinity Primary School, to be undertaken via Balfour Beatty Living Places, at a revised cost of £14,384 (initial cost £10,716) plus associated contingency, professional and statutory fees. A revised total cost up to the value of £21,000

The works will be funded from the existing schools capital maintenance budget