Decision details
To approve the expenditure of up to £7.5k for planned maintenance drainage improvement works at Hampton Dene Primary School from school capital maintenance funding
Decision Maker: Director of Children and Families (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
To approve the drainage improvement planned
maintenance works at Hampton Dene Primary School, to be undertaken
via Balfour Beatty Living Places, at an initial cost of £5317
plus associated contingency, professional and statutory fees. A
total cost up to the value of £7,500
Fund the works from the existing school capital maintenance
budget
Contact: Chris Jones, Strategic business intelligence manager Email: chris.jones@herefordshire.gov.uk Tel: 01432 261596.
Publication date: 03/09/2019
Date of decision: 29/08/2019