Approval of expenditure of up to £17k for planned maintenance fire precautions at Hampton Dene Primary School
Decision Maker: Assistant Director Education, Development and Skills (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
Approval of the fire precautions planned
maintenance works at Hampton Dene Primary School, to be undertaken
via Balfour Beatty Living Places, at an initial cost of
£14,007 plus associated contingency, professional and
statutory fees. A total cost up to the value of
£17,000.
The works will be funded from the existing school capital
maintenance budget
?
Contact: Chris Jones, Strategic business intelligence manager Email: chris.jones@herefordshire.gov.uk Tel: 01432 261596.
Publication date: 17/06/2019
Date of decision: 13/06/2019