Approval of the expenditure of up to £275k for planned maintenance re-roofing at Aylestone High School

Decision Maker: Assistant Director Education, Development and Skills (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To approve the re-roofing planned maintenance works at Aylestone High School, to be undertaken via Balfour Beatty Living Places, at an initial cost of £244,246 plus associated contingency, professional and statutory fees.

A total cost up to the value of £275,000; funded from the existing school capital maintenance budget

Contact: Chris Jones, Strategic business intelligence manager Email: chris.jones@herefordshire.gov.uk Tel: 01432 261596.

Publication date: 04/04/2019