Approval of expenditure of up to £203k for planned maintenance re-roofing at St Martins Primary School

Decision Maker: Assistant Director Education, Development and Skills (Historic)

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To approve the re-roofing planned maintenance works at St Martin’s Primary School, to be undertaken via Balfour Beatty Living Places, at an initial cost of £179,807 plus associated contingency, professional and statutory fees. A total cost up to the value of £203,000; funded from the existing school capital maintenance budget

Contact: Chris Jones, Strategic business intelligence manager Email: chris.jones@herefordshire.gov.uk Tel: 01432 261596.

Publication date: 04/04/2019

Date of decision: 04/04/2019