Early Works Instruction in respect of Aylestone School project for internal remodeling and refurbishment works.

Decision Maker: Service Director - Education, Skills and Learning

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Approve an Early Works Instruction under the Pre-Services
Construction Agreement in respect of the Aylestone School project
for enabling works.

The Early Works Instruction will be the refurbishment of a science
laboratory and creation of 3 general teaching classrooms from
existing classroom spaces at a cost of:

• Works £404,447.34
• Contingency £40,000

Contact: Annie Ahearne, Programme Coordinator Email: annie.ahearne3@herefordshire.gov.uk.