Decision details

Decision to approve expenditure for design and build of an integrated wetland scheme on Land at Tarrington and enter into a contract with JBA Bentley Ltd

Decision Maker: Corporate Director – Economy & Environment

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

To approve progression to the detailed design and construction phase of the Tarrington integrated wetland, forming part of phase 2 of the phosphate mitigation strategy referred to in the key decision of 29 February 2024.

To approve the expenditure of up to £1,396,208 (including £200,000 contingency) for the design and construction of the Tarrington wetland scheme, and to enter into a contract with JBA Bentley Ltd for delivery of the same.

The Delivery Director for Infrastructure be authorised to take all operational decisions necessary for the delivery of the scheme within the approved capital budget.

The Senior Project Manager be authorised, in consultation with the Project Board and with specialist council officers as appropriate, to manage and spend the budget and contingency stated below.

Financial Summary:
Wetland Design & Construction costs £1,121,958
Quantity Surveyor/Clerk of Works £25,000
Other Survey & Review fees £49,250
Contingency £200,000
Total: £1,396,208



Contact: Diane Rees, Senior Project Manager Email: diane.rees@herefordshire.gov.uk.

Publication date: 12/12/2024

Date of decision: 23/10/2024