Decision details
Variation to Framework Partnership between the council and NHS Herefordshire and Worcestershire Integrated Care Board (HWICB) relating to the commissioning of health and social care services in connection with the Better Care Fund.
Decision Maker: Corporate Director - Community Wellbeing
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
County of Herefordshire District Council and
NHS Herefordshire and Worcestershire Integrated Commissioning Board
(HWICB) form part of a Framework Partnership Agreement relating to
the commissioning of health and social care services in exercise of
the powers referred to in Section 75 of the 2006 Act and/or Section
13Z(2) and 14Z(3) of the 2006 Act as applicable (the
“Partnership Agreement”).
As part of the annual review of budgets and commissioning plans the
partners have agreed a revised financial plan for the financial
year 2023/24.
The Partners acknowledge agree and confirm that they waive the
requirements of clause 33 (Variation) in respect of the variations
set out in this Deed and further acknowledge, agree and confirm
that the Partnership Agreement shall be amended as follows:
1) The Partnership Agreement shall be varied in accordance with
Schedule 1 (Amendments to the Partnership Agreement).
2) The Partners have agreed to vary Schedule 1 (Financial
Contributions and Financial Governance) to the Partnership
Agreement as set out in Schedule 4 (Other Amendments).
3) The Partners have agreed to amend Schedule 3 (Scheme Template
& Schedules) to the Partnership Agreement to reflect the
revised financial plan as set out in Schedule 4 (Other
Amendments).
4) The Partners have reviewed the financial arrangements contained
in the Partnership Agreement and have agreed to revise Schedule 4
(Risk Share and Overspends) to the Partnership Agreement to reflect
the revised financial plan as set out in Schedule 4 (Other
Amendments).
5) The Partners have reviewed the performance managements contained
in the Partnership Agreement and have agreed to revise Schedule 6
(Performance Arrangements) to reflect the revised governance
structures for joint commissioning as set out in Schedule 4 (Other
Amendments).
6) The partners have reviewed the detailed financial plan and have
agreed to Schedule 11 (Financial Plan) to reflect the revised
schemes, services and contributions to each pooled fund.
7) The Partnership Agreement shall be varied as set out in Schedule
4 (Other Amendments).
A partnership arrangement under section 75 (s75) of the NHS Act
2006 enables partners to commission integrated health and social
care services to better meet the needs of service users than if the
partners were operating independently. Section 75 agreements
provide a contractual framework for the use of pooled funds between
the council and the ICB, to enable services to be delivered and
commissioned co-dependently.
The s75 agreement is a national requirement of the Better Care
Fund, set by NHS England under the NHS Act 2006.
The s75 covers the current financial year 2023/24. The national
deadline for approval of the s75 was 31 October 2023; at this point
negotiations were still ongoing between partners, the Regional BCF
Manager was kept appraised of negotiations and an agreement between
partners for final approval was subsequently reached.
Contact: Hilary Hall, Corporate Director Community Wellbeing Email: Hilary.Hall@herefordshire.gov.uk.
Publication date: 13/02/2024
Date of decision: 08/02/2024
Accompanying Documents: