Decision details
Decision to fund £3937.42 of Section 106 monies for “Highways & Transport” towards the supply and installation of two Speed Indicator Devices (SID) on the westbound approach of the A438 in Tarrington
Decision Maker: Director of Resources and Assurance (Historic)
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The Section 106 Contributions arise from one
Section 106 legal agreement:
Planning Reference GT / FIN Code Original Contribution S106
Allocation Expiry Date
P171777/F GT06 FIN1995 £15,275.00 £3937.42
11/02/2031
TOTAL £3937.42
The decision to fund £3937.42 will fully utilise the Section
106 Contribution.
£11,337.58 has been previously spent to implement a Traffic
Regulation Order (TRO). Speeding through Tarrington is an ongoing
problem and a recent speed survey completed by West Mercia Police
in September 2O22 showed 48,823 vehicles over 7 days and an 85th
percentile speed of 39mph in a 30mph speed limit. The
implementation of the TRO completed on 30/04/2021.
A full tendering exercise has been carried out in accordance with
Herefordshire Councils Contract Procurement Rules (CPR). The Tender
information has been included within appendix 1.
The procurement exercise resulted in a final contract value of
£7600 with nominated contractor ElanCity-UK. The
£3937.42 allocation from Section 106 will contribute towards
the total cost of the project.
Responsibility for monitoring the project and managing expenditure
within the total spend budget is to be with the Programme
Manager.
Contact: Andrew Lovegrove, Director of Resources and Assurance Email: Andrew.Lovegrove@herefordshire.gov.uk.