Decision details
Decision to fund £52,782, of Section 106 monies for “Education” towards extension to staff toilet provisions, installation of outdoor playground equipment and IT Wi-Fi expansion at Canon Pyon Academy
Decision Maker: Director of Resources and Assurance
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
The Section 106 Contribution arises from one
Section 106 legal agreements:
Planning Reference GT / FIN Code Original Contribution £
Expiry Date
P141917/F GT05 FIN1831 £52,782 14/10/2025
TOTAL £52,782
The decision to fund £52,782 will fully utilise the Section
106 Contribution.
From this contribution there has been no expenditure to date. The
expiry date is the contribution is 14/10/2025.
A full tender exercise has been completed and evaluated and
complies with Herefordshire Councils’s Contract Procedure
Rules (CPR’s). All tender returns and breakdowns have been
contained within the supporting information.
The full cost of the project is:
Toilet Expansion £42,185
Playground Equipment £9479.27
Outdoor Gym Equipment £5621.12
IT Wi-fi Expansion £12,056.86
TOTAL £69,342.25
The S106 contribution is £52,782. Canon Pyon Academy have
agreed to provide £16,560.25 to make up the difference.
Responsibility for monitoring the project and managing expenditure
within the total spend budget is to be with the Senior Project
Manager.
Contact: Andrew Lovegrove, Director of Resources and Assurance Email: Andrew.Lovegrove@herefordshire.gov.uk.
Publication date: 13/10/2022
Date of decision: 09/10/2022
Accompanying Documents: