Whitney on Wye Flood Damage Repairs – Contract Award

Decision Maker: Corporate Director – Economy & Environment

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

Following the decision by Cabinet on 23 July, 2020, the subsequent decision taken by the Council on the 4th August 2020, the works to repair all remaining sites were to be commissioned and delivered.

Consequently the Director Of Economy and Place took the decision on the 22 September 2020 that all remaining elements of the Fownhope work be delivered through the Public Realm Contract. The Whitney on Wye scheme be delivered as a Design and Build Commission. The various flood damaged sites be delivered through a framework commission.

The Fownhope works have been delivered, the framework of flood damaged sites is being delivered. The Whitney scheme went to tender However no returns have been received.

2 July 2021 the Director for Economy and Place took the decision to Whitney on Wye Scheme is delivered through the Public Realm Services Contract with the build element delivered through an open market contract which will follow once the design is complete.

A council compliant procurement exercise has been completed, this decision is to award the contract.
The tender price for the works is £187,100.94

Contact: Ross Cook, Corporate Director - Economy and Environment Email: ross.cook@herefordshire.gov.uk.

Publication date: 31/05/2022

Date of decision: 20/05/2022