That:
• All remaining elements of the Fownhope work (estimated
scheme value £1m including all management support) be
delivered through the Public Realm Services Contract;
• The Witney of Wye instability (estimated scheme value
£0.5m including all management support) be delivered as a
design and build commission;
• The Various flood damage Sites (estimated scheme value
£0.962m including all management support) be delivered
through a new framework contract aimed at providing a
‘post’ COVID opportunity directly to local SMEs;
and
• The Managing Agent support to the council’s own
project and contract management costs, as required to deliver these
schemes, is commissioned through the Public Realm Services
Contract.