Decision details
SURFACE DRESSING WORKS (JUNE) HEREFORDSHIRE
Decision Maker: Acting Assistant Director for Highways and Transport
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
To authorise the making of a Temporary Lane
Closure Order served under section 14(1) of the Road Traffic
Regulation Act 1984 to require a temporary closure of the roads
shown in Article 1 Schedule 1 of the Order as attached. The Order
shall come into effect on the 3rd June 2019 and is planned to be in
effect for 4 weeks, with each road being closed for the planned
duration show in Article 1, attached.
Contact: Clive Hall, Acting Assistant Director for Highways and Transport Email: cwhall@herefordshire.gov.uk Tel: 01432 260786.
Publication date: 07/05/2019
Date of decision: 07/05/2019
Accompanying Documents: