Decision details
Allocation of Basic Need Capital Grant for the Expansion of John Masefield High School and Weobley High School
Decision Maker: Cabinet member community services and assets
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
Purpose:
To seek approval to allocate and spend Department for Education (DfE) Basic Need Capital Grant funding to support the expansion of John Masefield High School and the relocation of modular accommodation to Weobley High School.
Decision:
That the Cabinet Member:
a) Approves, the delivery of the John Masefield High School expansion and the Weobley High School modular accommodation project within a total budget of £5.390M;
b) Delegates authority to the Service Director for Education, Skills and Learning to make all operational decisions required to deliver the works within the overall approved budget, and;
c) Delegates authority to the Service Director for Education, Skills and Learning to procure and award all necessary contracts required to deliver the programme of works.
Alternative options considered:
1. Do nothing - This option is not recommended. The council has a statutory duty to secure sufficient school places. John Masefield High School has been admitting above its published admission number (PAN) at the request of the council for a number of years due to increasing demand in the Ledbury area arising from demographic growth and significant housing development. Failure to expand the school would increase pressure on local secondary school places and reduce the council’s ability to meet parental preference and avoid additional transport costs.
2.
Retain the existing end-of-life mobile accommodation at
Weobley High School.
This option is not recommended as the existing accommodation is at
the end of its operational life and does not represent a
sustainable long-term solution for the school. The proposal to
relocate the modular village from Peterchurch Primary School provides improved
teaching accommodation, additional classroom and toilet facilities,
and represents better value for money through the reuse of an
existing council-owned asset.
3.
Reuse the modular village for an alternative purpose or dispose of
the asset.
Alternative reuse opportunities for the modular village were
explored, including potential nursery provision. However, planning
constraints associated with the suggested location meant that this
option was not considered deliverable. Disposal of the modular
village was also considered but is not recommended. The modular
accommodation was originally purchased with the intention of reuse
following completion of the Peterchurch
Primary School rebuild project, and disposal would likely realise
limited residual value compared to the educational and financial
benefits achieved through reuse at Weobley High School.
Reason Key: Expenditure;
Wards Affected: Ledbury South; Weobley;
Contact: Quentin Mee, Head of Educational Development Email: Quentin.Mee@herefordshire.gov.uk.
Publication date: 26/06/2026
Date of decision: 26/06/2026
Effective from: 03/07/2026
Accompanying Documents:
PDF 276 KB