Decision details
College Road Campus Roof
Decision Maker: Corporate Director – Economy & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
Decision to award contract to Central Roofing
and Building Services Ltd and approve the expenditure of up to
£680,101.98 for the replacement flat roof coverings and works
to roof light and roof mounted plant and equipment to facilitate
the roof covering replacement at Hereford College Road Campus, HR1
1EB.following a successful tender on the Council’s
procurement portal.
Approve the expenditure of up to £673,101.98 for the works,
which includes a contingency of up to £60,100.18.
Approve the expenditure of up to £7,000 for internal and
external professional fees.
Authority is delegated to the Capital Project Manager from
the
Corporate Director of Economy and Environment to act as spend
manager for the project. Responsibility for monitoring the
remaining works to be carried out by the Capital Project Manager
within the spend budget.