Decision to approve the expenditure of up to £76,000.00 for the capital emergency electrical works at Weobley High School

Decision Maker: Service Director - Education, Skills and Learning

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Decision:

Award a contract to National Grid and Melcon for the emergency electricalworks at Weobley High School Herefordshire.

Approve the expenditure of up to £71,000.00 for the works, which includes a contingency of up to £10,000.00

Approve the expenditure of up to £5,000.00 for internal and external
professional fees.

Responsibility for monitoring the programme to be carried out by the Capital Senior Project Manager within the spend budget.