Award of highway works associated with Public Rights of Way structures – PRoW Works Order 1 - Additional Funding
Decision Maker: Corporate Director – Economy & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
An additional requirement to increase the
overall service order budget by £13,554.89 has been
identified and is to be added to the service order. This increase
is due to additional construction requirements that have arisen
during delivery of the works and has been captured through the
appropriate contract protocols.
Contact: Callum Bush, TRO and PROW Team Leader Email: callum.bush@herefordshire.gov.uk Tel: 01432 383866.
Publication date: 06/06/2025
Date of decision: 06/06/2025