Decision details
S104 agreement in respect of land at The Poplars, Vineyard Lane, Hereford, HR1 2AW.
Decision Maker: Commercial and Investment Manager
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
1. The identified pipe route is the preferred
route by the statutory undertaker Dwr Cymru Welsh Water and
presents the only route for the adjacent landowner to service his
property.
2. The S104 agreement relates to the adoption of a waste pipe that
will be installed under Council owned land. Dwr Cymru Welsh Water
will adopt the pipe once it has been installed.
3. A Deed of Easement has been entered into to protect the
Council’s position and ensure the road is repaired in a like
for like fashion when the pipe has been laid.
4. Associated costs have been paid by the adjacent landowner.
Contact: Michelle Chadd Email: michelle.chadd4@herefordshire.gov.uk Tel: 01432 261552.
Publication date: 08/05/2025
Date of decision: 28/04/2025