Award a contract to carry out Building Fabric, Fire Stopping, Split Fire Alarm and Associated Improvements up to a value of £196,877.50 at No 8 Owen Street, Hereford
Decision Maker: Strategic Assets Delivery Director
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
To award a contract to S C Joseph Ltd. This
decision is to award the contract to S C Joseph Ltd to carry out
works at No 8 Owen Street, Hereford, HR1 2PJ following the
completion of a successful tender, evaluation and moderation
process.
Works to include carrying out Building Fabric, Fire Stopping, Split
Fire Alarm and associated Improvement works at No 8 Owen
Street.
To approve the works expenditure of up to £196,877.50 which
includes
£23,625.30 contingency and £15,750.20 for internal and
external fees of the tendered price.
Responsibility for delivering works to be carried out by the
Capital Senior Project Manager within the spend budget of the
Capital Building Improvement Programme.