Issue details
To approve expenditure of the two tier risk allocation at Marlbrook School
a) To authorise spend up to the value of up to
£10,200 from the two tier risk budget line for this capital
project.
The budget detailed in the cabinet report relating to this decision
to spend are as follow:
https://councillors.herefordshire.gov.uk/documents/s50073157/Marlbrook%20revised%20business%20case%20and%20budget%20report.pdf
The risk budget
Item Budget
Two tier risk £73,500
The risk budget was identified as two tier risk owned by the
council at the time of signing the contract. The value sits outside
the contract value.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 29/06/2020
Decision due: 22 June 2020 by Director of Children and Families (Historic)
Contact: Chris Baird, Director for children and families Email: cbaird@herefordshire.gov.uk Tel: 01432 260264.