That:

a)    The redevelopment of Maylord Orchards to create a new library and learning resource centre project is approved;

b)    Expenditure of up to £0.45m of the Maylord Orchard Library and Learning Resource Centre project capital programme allocation be approved to complete the detailed design stage of the project including seeking planning permission,; and

c)    The Corporate Director for Community and Wellbeing, following consultation with the Deputy Section 151 Officer and in consultation with the Cabinet member commissioning, procurement and assets, be authorised take all operational decisions necessary to complete the detailed design stage and seek planning approval within the £0.45m approved budget.