Decision details
To approve the design and construction of Widemarsh St enhancement scheme
Decision Maker: Corporate Director – Economy & Environment
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
1) The council entered into a grant agreement
with the Marches LEP on 15 December 2020 and varied on 20 December
2021 to jointly fund a package of improvement works throughout
Hereford City Centre. This scheme of works must be completed by 31
March 2024.
2) The report for the Cabinet Member decision of 7 October 2021 set
out that this work will be commissioned through the Balfour Beatty
Living Places public realm contract. This procurement route has
been identified to achieve the timescales and utilising continuity
of knowledge through the works and schemes that BBLP have already
provided.
3) It was noted in the above report that the budgets were high
level and that there was significant risk that these would
vary.
4) The existing Widemarsh St design scheme completed in 2011 has
been subject to a number of specialist technical design and safety
reviews. All have concluded that the scheme is fully in line with
design guidance and best practice.
5) The 7 October 2021 Cabinet Member decision set out the HCCI
programme with a budget to enhance Widemarsh St, in recognition
that some members of the public continue to experience difficulties
in traversing the street despite the scheme compliance.
6) A wide variety of options for improving the street have been
explored and discounted.
7) The key factors to consider were:
• The visual impact of the street
• The ease of use for pedestrians in terms of the
pavement
• Safety of pedestrians regarding the use of the street by
vehicles
• Cost
• Drainage
8) Taking all of these factors into account the recommended option
is a full lift of the road surface to remove the 50mm upstand with
replacement of the kerb and provision of a linear drainage
system.
9) The estimated total budget envelope for the scheme design and
construction/delivery is £1.3m. This will include full design
including any additional surveying, drainage modelling etc and the
construction including the lifting of 690m² road surface,
incorporating new porphyry sets, replacement of kerbing, provision
of drainage, traffic management, communications and contingency. It
is estimated that the construction works will be an approximately
16 week programme.
10) It should be noted that the use of new porphyry sets is more
cost efficient that lifting the existing sets, cleaning off of
mortar and relaying. The old sets will be recycled.
11) The re-profile of HCCI budgets as set out in the Record of
Officer Decision dated 6 October 2022 increased the initial
provisionally estimated budget to account for the anticipated spend
required for this Cabinet supported scheme. ie there is sufficient
capital budget to carry out this scheme within the HCCI package of
works.
Contact: Susan White, Programme Manager Email: Susan.White2@herefordshire.gov.uk Tel: 01432 260070.
Publication date: 15/11/2022
Date of decision: 11/11/2022