Issue details
To approve the expenditure of up to the value of £205,550 for Distribution
To award the following contracts to carry out
the Distribution Board
works.
Award CM Ward for Batch 1;
The Aconbury Centre, Withington Primary, Much Birch Primary.
To authorise the expenditure of up to £28,780, of which
includes a
contingency of up to £2,619.
Award CF Roberts for Batch 2, 3 & 4;
2 - Garway Primary, Clifford Primary, Kington Primary.
3 - Ledbury Primary
4 - Trinity Primary.
To authorise the expenditure of up to £156,400, of which
includes a
contingency of up to £14,220.
To authorise the expenditure of up to £20,370 for external
and internal
professional fees.
Responsibility for monitoring the project to be carried out by the
Capital
Project Manager within the spend budget.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 07/02/2022
Decision due: 7 February 2022 by Service Director - Education, Skills and Learning
Contact: Ceri Morgan, Education Strategic Projects Email: ceri.morgan@herefordshire.gov.uk.