Decisions
01/10/2026 - Decision to extend the Sensory Impairment Service contract by two months ref: 11367 Recommendations Approved
Decision Maker: Corporate Director - Community Wellbeing
Decision published: 08/10/2026
Effective from: 01/10/2026
Decision:
To approve a two-month extension of the
Sensory Impairment Service contract with Vision Links, from 1
February 2027 to 31 March 2027, on the existing terms and service
requirements.
The maximum value of the extension is £26,000, comprising
£19,167 for service delivery and up to £6,833 for aids
and equipment, with equipment expenditure incurred only where
required.
Lead officer: Louise Harper
02/10/2026 - Decision to approve a nine-month extension to the Adults Independent Advocacy Service contract with Onside Ltd ref: 11366 Recommendations Approved
Decision Maker: Corporate Director - Community Wellbeing
Decision published: 08/10/2026
Effective from: 02/10/2026
Decision:
To approve a nine-month extension to the
Adults Independent Advocacy Service contract with Onside Ltd, from
1 November 2026 to 31 July 2027, at a value of
£155,960.24.
The extension will continue the existing service and contractual
deliverables without any material change to scope.
The revised aggregate contract value will be £1,247,682.00.
Legal Services will formalise the extension through a Deed of
Variation.
Lead officer: Louise Harper
01/10/2026 - To vary the Pre-Construction Services Agreement (PCSA) with Speller Metcalfe Malvern Limited for the refurbishment of John Venn Building ref: 11365 Recommendations Approved
Decision Maker: Corporate Director – Economy & Environment
Decision published: 08/10/2026
Effective from: 01/10/2026
Decision:
To vary the Pre-Construction Services
Agreement to Speller Metcalfe up to the value of £115,972 for
enabling works to inform the development of the design, cost,
programme, and risk profile of the project.
The Corporate Director, Economy and Environment approves the
delegated authority to the Programme Manager Capital- Economy and
Environment or the equivalent or above within economy and
environment to take all operational decisions relating to the award
of contracts for the John Venn redevelopment project and for the
2025-2028, 2026-2029 and 2024-2027 Estates Capital Programme.
Authority is delegated to the Capital Project Manager from
the
Corporate Director of Economy and Environment to act as spend
manager for the programmes. Responsibility for monitoring the
remaining works to be carried out by the Capital Project Manager
within the spend budget.
The Pre-Construction Services Agreement (PCSA) was tendered using a
compliant procurement process via the Procure Partnership
framework.
This variation will enable non-structural strip out works to take
place which will inform the design for the refurbishment of the
building and provide benefits to the programme.
The existing Pre-Construction Services Agreement in place for this
project allows for the inclusion of these works within the contract
through the Additional Works mechanism.
Lead officer: Laura Matthews
24/09/2026 - Decision Regarding the sale of Wilson house car park ref: 11364 Recommendations Approved
Decision Maker: Commercial and Investment Manager
Decision published: 08/10/2026
Effective from: 24/09/2026
Decision:
To complete the sale of Wilson house car
park.
After careful consideration, it has been determined that Wilson
House car park is surplus to the strategic requirements of the
council’s property portfolio. As such, a decision has been
made to proceed with their sale. This course of action is expected
to generate a substantial financial return for the council, thereby
supporting broader objectives and enabling the reallocation of
resources to higher-priority assets and services. The sale aligns
with the council’s commitment to effective asset management.
A decision was made to obtain a red book valuation on the site so
that the council could have an external valuation without any bias
and negotiate the best value for both parties.
Lead officer: Michelle Chadd
28/09/2026 - Grant of Temporary Lease in respect of Unit 30, 5 Gomond Street, Maylord Orchards Centre, Hereford. ref: 11363 Recommendations Approved
Decision Maker: Acting Assistant Director for Highways and Transport
Decision published: 08/10/2026
Effective from: 28/09/2026
Decision:
To grant a Tenancy at Will for Unit 30, 5
Gomond Street, Maylord Orchards Centre, Hereford.
1. The unit is currently vacant.
2. We have been approached by a retailer wishing to run a Christmas
Shop over the festive period.
3. The terms agreed are on an inclusive basis with the Rent
covering for payment of the service charge, insurance and business
rates. The Tenant will be responsible for paying utilities and
leaving the property in acceptable condition.
Lead officer: Michelle Chadd
01/10/2026 - Award of Access Group contract for Mosaic, Synergy and associated systems ref: 11362 Recommendations Approved
Decision Maker: Corporate Director - Community Wellbeing
Decision published: 08/10/2026
Effective from: 01/10/2026
Decision:
To finalise and execute a five-year contract
with The Access Group for the provision of Mosaic, Synergy, Abacus
and Core+, via direct award under the Yorkshire Purchasing
Organisation (YPO) 1095 framework (Lot 12),(Health and Social Care
Software Systems for UK public sector organisations) at total cost
of £3.4m, for the period 1 October 2026 to 30 September 2031,
including hosting arrangements and delivery protection
provisions.
Corporate Director Community Wellbeing to make all operational
decisions relating to the implementation of the contract
awarded.
Lead officer: Marie Gallagher
02/10/2026 - The decision to not adopt the Bredenbury and District Group Neighbourhood Development Plan due to the lack of Nutrient Neutrality Policy within the plan ref: 11361 Recommendations Approved
Decision Maker: Service Director Economy and Growth
Decision published: 06/10/2026
Effective from: 02/10/2026
Decision:
The decision has been made not to adopt the
Bredenbury and District Group Neighbourhood Development Plan
(referred to as ‘The NDP’)
Lead officer: Siobhan Riddle
02/10/2026 - The decision to not adopt the Stretton Grandison Group Neighbourhood Development Plan due to the lack of Nutrient Neutrality Policy within the plan. ref: 11360 Recommendations Approved
Decision Maker: Service Director Economy and Growth
Decision published: 06/10/2026
Effective from: 02/10/2026
Decision:
The decision has been made not to adopt the
Stretton Grandison Group
Group Neighbourhood Development Plan (referred to as ‘The
NDP’)
Lead officer: Siobhan Riddle
02/10/2026 - The decision to not adopt the Ashperton Neighbourhood Development Plan due to the lack of Nutrient Neutrality Policy within the plan. ref: 11359 Recommendations Approved
Decision Maker: Service Director Economy and Growth
Decision published: 06/10/2026
Effective from: 02/10/2026
Decision:
The decision has been made Not to adopt the
Ashperton Neighbourhood Development Plan (referred to as ‘The
NDP’)
Lead officer: Siobhan Riddle
05/10/2026 - Building a Strategic Partnership between Herefordshire and Zhytomyr Oblast, Ukraine
To agree the outcomes for the proposed
Memorandum of Understanding, the implementation plan and resource
requirements to support the long-term Herefordshire-Zhytomyr
Strategic Partnership
Decision Maker: Cabinet
Decision due date: 17/12/2026
Wards affected: (All Wards);
Lead officer: Hilary Hall
Notice of decision: 05/10/2026
Anticipated restriction: Open
05/10/2026 - Empty Property Strategy 2026-2029
To approve the Empty Property Strategy
2026-2029 and associated Grant Scheme Overview.
To delegate authority for Grant Scheme approvals and operational
decisions to the Head of Housing Services.
Decision Maker: Cabinet member adults, health and wellbeing
Decision due date: 31/01/2027
Wards affected: (All Wards);
Lead officer: Michelle Powell
Notice of decision: 05/10/2026
Anticipated restriction: Open
29/09/2026 - Work programme ref: 11337 Recommendations Approved
Decision Maker: Audit and Governance Committee
Made at meeting: 29/09/2026 - Audit and Governance Committee
Decision published: 01/10/2026
Effective from: 29/09/2026
Decision:
The committee considered the work programme. Members noted that the next meeting would include updates on internal audit and risk management. It was requested that the Cabinet Member responsible for environmental matters be invited to provide information relevant to the environmental risks previously raised by the Environment Scrutiny Committee initally through Cabinet.
The committee also noted forthcoming items on the whistleblowing policy, governance matters and the waste contract.
RESOLVED: That, subject to the updates made by the committee, the work programme be noted.
16/09/2026 - To make provisional Tree Preservation Order 717 Land adjacent 28 Chichester Close Hereford ref: 11358 Recommendations Approved
Decision Maker: Officer Decisions - Economy and Enviroment
Decision published: 01/10/2026
Effective from: 16/09/2026
Decision:
To serve a provisional TPO
Lead officer: Ruth Jackson
23/07/2026 - To confirm Tree Preservation Order 705 78 Hampton Park Road Hereford ref: 11357 Recommendations Approved
Decision Maker: Officer Decisions - Economy and Enviroment
Decision published: 01/10/2026
Effective from: 23/07/2026
Decision:
To confirm a TPO
Lead officer: Ruth Jackson
24/09/2026 - Decision to fund up to £166,798.88 of Section 106 “Sports” and “Education” monies for works to create a New Grass Sports Field at Fairfield High School, Peterchurch. ref: 11356 Recommendations Approved
Decision Maker: Service Director - Education, Skills and Learning
Decision published: 01/10/2026
Effective from: 24/09/2026
Decision:
Decision to fund up to £166,798.88 of
Section 106 “Sports” and “Education” monies
for works to create a New Grass Sports Field at Fairfield High
School, Peterchurch.
Lead officer: Melissa Walker
29/09/2026 - Decision to fund up to £80,608.37 of Section 106 “Education” monies for works to create an expansion of the KS1 toilets at St Paul’s CofE Primary School, Hampton Dene Road, Tupsley, Hereford. ref: 11355 Recommendations Approved
Decision Maker: Service Director - Education, Skills and Learning
Decision published: 01/10/2026
Effective from: 29/09/2026
Decision:
Decision to fund up to £80,608.37 of
Section 106 “Education” monies for works to create an
expansion of the KS1 toilets at St Paul’s CofE Primary
School, Hampton Dene Road, Tupsley, Hereford.
Lead officer: Melissa Walker
29/09/2026 - Decision to fund up to £145,500 of Section 106 “Education” monies for works to create a new food technology classroom at John Masefield High School and Sixth Form Centre. ref: 11354 Recommendations Approved
Decision Maker: Service Director - Education, Skills and Learning
Decision published: 01/10/2026
Effective from: 29/09/2026
Decision:
Decision to fund up to £145,500 of
Section 106 “Education” monies for works to create a
new food technology classroom at John Masefield High School and
Sixth Form Centre.
Lead officer: Melissa Walker
24/09/2026 - Decision to fund up to £180,000 of Section 106 “Education” (secondary and Post-16) monies for works to create a covered area to the rear of the dining hall at John Masefield High School and Sixth Form Centre ref: 11353 Recommendations Approved
Decision Maker: Service Director - Education, Skills and Learning
Decision published: 01/10/2026
Effective from: 24/09/2026
Decision:
Decision to fund up to £180,000 of
Section 106 “Education” (secondary and Post-16) monies
for works to create a covered area to the rear of the dining hall
at John Masefield High School and Sixth Form Centre
Lead officer: Melissa Walker
28/09/2026 - Wilton Road, Ross on Wye – Award of Contract for Rock Trap and wall installation. ref: 11352 Recommendations Approved
Decision Maker: Major Contracts Programme Director
Decision published: 01/10/2026
Effective from: 28/09/2026
Decision:
To approve the appointment of Owen Pell Ltd to
undertake civil engineering works at Wilton Road rock face,
including installation of a rock trap and drainage
improvements.
The Wilton Road rock face scheme has been developed to mitigate the
risk of rock fall from the adjacent rock face and improve the
safety and resilience of the highway network through construction
of a rock trap system involving a precast concrete barrier with a
stone-faced finish, drainage improvements and associated highway
reinstatement works.
Lead officer: Fiona Miles
24/09/2026 - Decision to agree assignment of lease at 1&2 Markyes Close, Ross-onWye ref: 11351 Recommendations Approved
Decision Maker: Commercial and Investment Manager
Decision published: 01/10/2026
Effective from: 24/09/2026
Decision:
Decision to agree assignment of lease at
1&2 Markyes Close, Ross-on-Wye
Lead officer: Rachel Fletcher
26/08/2026 - Commercial Rd / Blueschool Street, Hereford – Traffic Signal Junction upgrade scheme ref: 11350 Recommendations Approved
Decision Maker: Major Contracts Programme Director
Decision published: 01/10/2026
Effective from: 26/08/2026
Decision:
To approve the appointment of Telent
Technology Services Limited to undertake the installation and
commissioning of traffic signal improvements at Commercial Rd &
Blueschool St, Hereford. The existing traffic signals have reached
the end of their design life and are experiencing increasing
failures. In accordance with framework procedures, a direct award
is proposed to Telent Technology Services Limited, as they are the
sole contractor for delivering Traffic Signal Improvement and
Maintenance Works.
To deliver the investment as set out in the Cabinet Member Decision
Report, the Council needs to award a contract for traffic signal
upgrade works to Telent Technology Services Limited.
Lead officer: Fiona Miles
21/09/2026 - Decision to grant a renewal lease in respect of Unit 26 -27, 1-3 Brewers Passage, Maylord Orchards Centre, Hereford ref: 11349 Recommendations Approved
Decision Maker: Commercial and Investment Manager
Decision published: 01/10/2026
Effective from: 21/09/2026
Decision:
Decision to grant a renewal lease to Landau in
respect of Unit 26 -27, 1-3
Brewers Passage, Maylord Orchards Centre, Hereford.
Lead officer: Rachel Fletcher
30/09/2026 - Decision to exercise the final one-year extension of the Healthwatch Herefordshire contract ref: 11348 Recommendations Approved
Decision Maker: Corporate Director - Community Wellbeing
Decision published: 01/10/2026
Effective from: 30/09/2026
Decision:
To approve the exercise of the final one-year
extension option under the Healthwatch Herefordshire contract,
extending the contract from 1 October 2026 to 30 September
2027.
Lead officer: John Burgess
18/09/2026 - Traffic Signal System Improvements – Aylestone Hil/Commercial Road Corridor ref: 11347 Recommendations Approved
Decision Maker: Major Contracts Programme Director
Decision published: 29/09/2026
Effective from: 18/09/2026
Decision:
To commission Yunex to implement recommended
improvements to the traffic signal system at the junctions of
Commercial Road, Stonebow Road, Station Road, Aylestone Hill. The
cost for the scheme is £70,179, with a further £10,000
for validation of the traffic signal network in the vicinity of the
changes. A further 10% contingency will be added to the
contract.
Lead officer: Bruce Evans
28/09/2026 - Herefordshire Care Home Partnerships Framework ref: 11336 Recommendations Approved
To approve the procurement of a new multi
provider partnership framework for the provision of care home
placements and related services. The Council is looking to
formalise partnership arrangements for a minimum of 500-550
placements across all providers.
Estimated value of up to £320m across the framework term
(maximum of 8 years).
Decision Maker: Cabinet member adults, health and wellbeing
Decision published: 28/09/2026
Effective from: 03/10/2026
Decision:
That:
a) the procurement of a Care Home Partnership Framework for adults in Herefordshire be approved at a total estimated cost of up to, but not exceeding, £484.3 million over an 8 year period; and
b) authority be delegated to the Corporate Director for Community Wellbeing to award and enter into contracts with the successful providers following completion of the procurement process; and
c) to approve any operational decisions, extensions, variations and contractual matters within the approved budget and in accordance with the Council's Contract Procedure Rules.
Wards affected: (All Wards);
Lead officer: Ros Murphy
28/09/2026 - Approval for draw down of Budget for Equipment and Aids within the Sensory Impairment Service Procurement ref: 11345 Recommendations Approved
To approve the draw down of the additional
equipment budget for the Sensory Impairment Service.
Decision Maker: Corporate Director - Community Wellbeing
Decision published: 28/09/2026
Effective from: 03/10/2026
Decision:
That:
a) an equipment and aids budget of up to £259,000 (£37,000 per annum) be approved for inclusion within the Sensory Impairment Service procurement; and
b) the total approved value of the procurement be increased to £780,000 over the initial five-year term and £1,092,000 over the full potential seven-year term, inclusive of any extensions.
Lead officer: John Burgess
22/09/2026 - Q2 Performance Report 2026-27
To review performance for Quarter 2 (Q2)
2026/27 and to report the performance position across all
Directorates for this period.
Decision Maker: Cabinet
Decision due date: 26/11/2026
Wards affected: (All Wards);
Lead officer: Jessica Karia-Fitzgerald
Notice of decision: 22/09/2026
Anticipated restriction: Open
10/09/2026 - Parking Enforcement Policy 2026
To approve the implementation of a revised
Parking Enforcement Policy to include the policies relating to the
implementation of virtual permits.
Decision Maker: Cabinet member roads and regulatory services
Decision due date: 30/10/2026
Wards affected: (All Wards);
Lead officer: Michael Barnes
Notice of decision: 10/09/2026
Anticipated restriction: Open
10/09/2026 - To re-commission the Technology Enabled Care Service in Herefordshire
The existing contract for the Technology
Enabled Care Service (TECS), including call monitoring, ends on 31
March 2027. Therefore, any new service arrangements will need to
commence from 1 April 2027.
Decision Maker: Cabinet member adults, health and wellbeing
Decision due date: 03/12/2026
Wards affected: (All Wards);
Lead officer: Sharon Amery
Notice of decision: 10/09/2026
Anticipated restriction: Open
02/09/2026 - Procurement of Parking and Virtual Permitting Software
To approve the procurement of Parking
Enforcement and Virtual Permitting Software contract for a maximum
of 5 years with an estimated value in excess of £500k
.
Decision Maker: Cabinet member roads and regulatory services
Decision due date: 30/10/2026
Wards affected: (All Wards);
Lead officer: Michael Barnes
Notice of decision: 02/09/2026
Anticipated restriction: Open
01/09/2026 - Highway Infrastructure Asset Management Policy and Strategy
To seek approval from the Cabinet Member
(Roads and Regulatory Services) for the proposed revision of the
Policy and Strategy for the delivery of Highway Infrastructure
Asset Management. These documents establish the framework for the
principles which are applied to the maintenance of our highway
network.
Decision Maker: Cabinet member roads and regulatory services
Decision due date: 30/10/2026
Wards affected: (All Wards);
Lead officer: Mark Lewis
Notice of decision: 01/09/2026
Anticipated restriction: Open
30/09/2026 - Merton Meadow Flood Alleviation Scheme ref: 11346 Recommendations Approved
Approval for additional expenditure due to the
impact of unprecedented levels of rainfall and flooding on the site
during January to March 2026
Decision Maker: Corporate Director – Economy & Environment
Decision published: 18/08/2026
Effective from: 07/10/2026
Decision:
a) To approve expenditure of up to £250,000 to meet the additional cost incurred on the Merton Meadow Flood Alleviation scheme due to unprecedented rainfall incurred during the construction period leading to delays and increased groundwater levels, and;
b) To delegate to the Director for Growth all operational decisions in finalising the project.
Wards affected: Widemarsh;
Lead officer: Roger Allonby, Stephen Holland
03/08/2026 - Connect to Work Programme
To approve the procurement of the Connect to
Work Individual Placement and Support (IPS) Programme in
Herefordshire using the Open Procedure in accordance with the
Procurement Act 2023. The programme is fully funded through a grant
provided by the Department for Work and Pensions (DWP).
To approve the award of a contract to the bidder achieving the
highest overall score against the published evaluation criteria for
a period of up to three years and six months, commencing in October
2026, with a total contract value of up to £1.22
million.
To delegate operational responsibility for the delivery of the
Connect to Work programme in Herefordshire to the Service Directors
for Economy and Growth and Education, Skills and Learning, acting
in consultation with the Cabinet Member for Economy and
Growth.
Decision Maker: Cabinet member economy and growth
Decision due date: 23/10/2026
Wards affected: (All Wards);
Lead officer: Alexia Heath
Notice of decision: 03/08/2026
Anticipated restriction: Open
27/07/2026 - Early Help Task and Finish Group - final report
To provide Cabinet with the final report of
the Children and Young People Scrutiny Committee's Early Help task
and group, looking at the provision of early help in
Herefordshire.
Decision Maker: Cabinet
Decision due date: 22/10/2026
Wards affected: (All Wards);
Lead officer: Danial Webb
Notice of decision: 27/07/2026
Anticipated restriction: Open
17/07/2026 - Skills Bootcamps Herefordshire 2027/2028 Financial Year
To approve the submission of a delivery plan
to the Department for Work and Pensions (DWP) for Skills Bootcamps
funding of £1.5 million for the 2027/28 financial year.
To agree that Herefordshire Council will act as the accountable
body for the management, administration and commissioning of the
funding, once approved by DWP, including any subsequent Skills
Bootcamps allocations awarded to the council.
To delegate to the Service Director for Economy and Growth and
Service Director for Education, Skills and Learning, all
operational decisions necessary to implement and deliver the
programme, including the appointment of training provider(s) and
the management of associated funding and contractual
arrangements.
Decision Maker: Cabinet member economy and growth
Decision due date: 23/10/2026
Wards affected: (All Wards);
Lead officer: Alexia Heath
Notice of decision: 17/07/2026
Anticipated restriction: Open
14/07/2026 - High Needs Budget 2027/28
To propose the High Needs Budget for 2027/28
to the Cabinet Member Children and Young People.
Decision Maker: Cabinet member children and young people
Decision due date: 29/03/2027
Wards affected: (All Wards);
Lead officer: Stacey Carter
Notice of decision: 14/07/2026
Anticipated restriction: Open
14/07/2026 - Schools, Central School Services and Early Years Budget 2027/28
To approve School Forum’s recommended
budget proposals for school budgets, central school
services and early years within the Dedicated Schools Grant (DSG)
for 2027/28.
Decision Maker: Cabinet member children and young people
Decision due date: 27/01/2027
Wards affected: (All Wards);
Lead officer: Stacey Carter
Notice of decision: 14/07/2026
Anticipated restriction: Open
14/07/2026 - Risk Management Update Q2 2026/27
To provide an update on the status of
corporate risks at the end of Quarter 2 2026/27 (September 2026)
and
provide assurance that risks are being managed effectively across
the council.
Decision Maker: Cabinet
Decision due date: 26/11/2026
Wards affected: (All Wards);
Lead officer: Stacey Carter, Rachael Sanders
Notice of decision: 14/07/2026
Anticipated restriction: Open
14/07/2026 - Q2 2026/27 Budget Report
To report the forecast position for 2026/27 at
Quarter 2 (September 2026), including explanation and
analysis
of the drivers for the material budget variances, and to outline
current and planned recovery activity to
reduce the forecast overspend.
To provide assurance that progress has been made towards delivery
of the agreed revenue budget and
service delivery targets, and that the reasons for major variances
are understood and are being
addressed to the cabinet’s satisfaction.
Decision Maker: Cabinet
Decision due date: 26/11/2026
Wards affected: (All Wards);
Lead officer: Stacey Carter, Rachael Sanders
Notice of decision: 14/07/2026
Anticipated restriction: Open
13/07/2026 - South Bank Close and Ivy Close Lease Arrangements
To approve Midland Hearts request to rescind
their lease of South Bank Close and Ivy Close.
To approve the procurement of a new lease holder for these
properties.
Decision Maker: Cabinet member community services and assets
Decision due date: Before 30/10/2026
Wards affected: Eign Hill;
Lead officer: Hannah McSherry
Notice of decision: 13/07/2026
Anticipated restriction: Open
04/06/2026 - Recommissioning of Drugs & Alcohol Recovery Services
To obtain approval to recommission drug and
alcohol recovery services in Herefordshire for an initial five-year
period (2028–2033), with the option to extend the contract by
a further two years. (2033–2035).
Decision Maker: Cabinet
Decision due date: 17/12/2026
Wards affected: (All Wards);
Lead officer: Natalie Johnson-Stanley
Notice of decision: 04/06/2026
Anticipated restriction: Open
20/05/2026 - Public Notices
To approve a contract via a direct award
process for the placing of public notices in newspapers circulating
within Herefordshire.
Decision Maker: Cabinet member finance and corporate services
Decision due date: 30/10/2026
Wards affected: (All Wards);
Lead officer: Ed Bradford
Notice of decision: 20/05/2026
Anticipated restriction: Open
13/05/2026 - To re-commission the home care framework in Herefordshire
To approve the re-commissioning of the
council's home care framework, called Services In Your Home (SIYH),
in Herefordshire. The new SIYH framework needs to be operational by
1 May 2027.
Decision Maker: Cabinet member adults, health and wellbeing
Decision due date: 21/10/2026
Wards affected: (All Wards);
Lead officer: Sharon Amery
Notice of decision: 13/05/2026
Anticipated restriction: Open
08/05/2026 - Establish a new Alternative Provision Centre capital spend
To approve the spend of the capital allocation
to establish a new Alternative Provision Centre
Decision Maker: Cabinet member community services and assets
Decision due date: 21/10/2026
Wards affected: (All Wards);
Lead officer: Quentin Mee
Notice of decision: 01/05/2026
Anticipated restriction: Open
28/04/2026 - Travel Plan Strategy
The purpose of this report is to seek Cabinet
approval for an updated Travel Plan process for Herefordshire. The
updated approach sets out a clearer, more consistent and
outcome-focused process for the development, implementation and
monitoring of travel plans across new developments, existing
organisations and key trip-generating sites.
Decision Maker: Cabinet
Decision due date: 22/10/2026
Wards affected: (All Wards);
Lead officer: Ffion Horton
Notice of decision: 25/04/2026
Anticipated restriction: Open
27/04/2026 - Relocation of Herefordshire Pupil Referral Units Capital Spend
To approve the spend of the capital allocation
to relocate Herefordshire Pupil Referral Units onto a single
site.
Decision Maker: Cabinet member community services and assets
Decision due date: 21/10/2026
Wards affected: (All Wards);
Lead officer: Quentin Mee
Notice of decision: 27/04/2026
Anticipated restriction: Open
30/01/2026 - Herefordshire Adult Social Care Prevention Strategy
The purpose of the report is to approve the
2026-2036 Herefordshire Adult Social Care Prevention
Strategy
Decision Maker: Cabinet member adults, health and wellbeing
Decision due date: 30/11/2026
Wards affected: (All Wards);
Lead officer: David Collyer
Notice of decision: 30/01/2026
Anticipated restriction: Open
22/01/2026 - Update on the Phase 2 Phosphate Mitigation Schemes
To provide Cabinet with an update regarding
the Phosphate Mitigation Wetland schemes
Decision Maker: Cabinet
Decision due date: 26/11/2026
Wards affected: (All Wards);
Lead officer: Gemma Dando, Richard Vaughan
Notice of decision: 22/01/2026
Anticipated restriction: Open