Decision to spend from the Property Services Estates Capital Works Programme to upgrade resilience to various properties.
The current equipment at these sites consists
of old analogue modems
which are now obsolete and at risk of failure and therefore loss of
remote
energy control.
An Exemption to Contract Procedure Rules was sought and approved
to
procure the works direct from Trend as the council’s BMS
system is a
closed protocol system manufactured by Trend Controls Limited and
they
have provided quotations amounting to £8,911.36 to upgrade
both sites.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 02/07/2021
Decision due: 24 June 2021 by Assistant Director for Technical Services
Contact: Chris Jenner, Assistant director for technical services Email: cjenner@herefordshire.gov.uk Tel: 01432 261941.