Appointment of Contractor for Initial Construction Works for New Permanent Accommodation at Marlbrook Primary School
04/06/2019 - Appointment of Contractor for Initial Construction Works for New Permanent Accommodation at Marlbrook Primary School
To award a letter of intent to Morgan Sindall
for the design and construction of the new permanent accommodation
and additional on-site car parking at an initial cost of
£744,856 plus associated client contingency and professional
fees. A total cost up to the value of £800,000. This will
cover:
• The design to be completed in detail and the full works
agreed
• All necessary surveys to be undertaken
• The creation of a south car park with associated drainage
and attenuation
• The widening of the entrance to the south side of the
site
• Internal remodeling to create an additional classroom
required for September 2019
• Conversion of an attic space to provide a staffroom (the
existing staffroom is required for an additional classroom)
• The creation of netball courts by infilling the existing
cycle track
• Morgan Sindall enabling works and preliminaries
The costs for the design and surveys were included in a previous
record of officer decision dated 24 September 2018. This authorized
expenditure up to £250,000. This decision is to authorize the
additional spend required to cover the extra items of work pending
the signing of the main contract, that is, an additional
£550,000.
The full cost of the scheme will be signed off at a later date once
the design has been completed. A further officer decision under the
delegated powers granted to the director of children’s
wellbeing by cabinet will be required to sign off the full
contract.
The design consultants selected and engaged by Morgan Sindall are
Quattro Design Architects, who were architects for the recently
completed Colwall Primary School new build.