Issue details
Decision to spend on the Shirehall Courtroom Ceiling Remedial Works
Additional structural defects have been found,
through surveys and structural calculations. This has resulted in
additional works to both court rooms 1 and 2, which include for
additional structure steel work to both courtrooms, removal of the
lower ceiling in court room 2, additional scaffolding structural
support and supporting design work.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 16/02/2021
Decision due: 25 January 2021 by Director of Economy and Place (Historic)
Contact: Chris Jenner, Assistant director for technical services Email: cjenner@herefordshire.gov.uk Tel: 01432 261941.