Approval of the expenditure of up to £10,387 from the Capital maintenance Schools’ Budget for safeguarding fencing works to Ashfield Park Primary School.
Award Balfour Beatty the contract to complete
the safeguarding fencing
works for the remaining elevation of the school at Ashfield Primary
School up to the value of £10,387 to include a contingency
value of up to £950 from the contingency allocation.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 03/11/2020
Decision due: 3 November 2020 by Assistant Director Education, Development and Skills (Historic)
Contact: Ceri Morgan, Education Strategic Projects Email: ceri.morgan@herefordshire.gov.uk.