Decision to deliver improvement works at Leominster MAO
Following the decision to deliver the
improvement works at Leominster MAO the BWOW programme Board
requested and approved a revised layout for the building which
increased the scheme cost by £30k and extended the programme
by two weeks.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 19/06/2020
Decision due: 19 June 2020 by Director of Economy and Place (Historic)
Contact: Chris Jenner, Assistant director for technical services Email: cjenner@herefordshire.gov.uk Tel: 01432 261941.
Decisions