Issue details
South Wye Transport Package - Southern Link Road (SLR) land acquisitions.
The owner of this parcel of land within the
CPO was only prepared to contract with the council prior to the CPO
Inquiry on the basis of an outright purchase, unlike all other
agreements which have been negotiated and agreed on the basis of an
option agreement enabling the council to acquire the land on
confirmation of the CPO and SRO or earlier if required. However as
this land is located at the eastern end of the scheme and has
direct access onto the highway in the event that the scheme does
not progress the land is capable of being resold, in the event that
the vendor does not exercise their option to purchase back the
land. On completion of the purchase the landowner will withdraw
their objection to the CPO and SRO.
Decision type: Non-key
Decision status: Recommendations Approved
Notice of proposed decision first published: 03/03/2020
Decision due: 24 September 2018 by Chief executive
Contact: Mairead Lane, Acting Assistant Director for Highways and Transport / Head of Infrastructure Delivery Email: mlane@herefordshire.gov.uk Tel: 01432 260944.
Decisions