Issue - decisions

Award a contract to Jackwolf Group and approve the expenditure of up to £415,274 for the provision of heating works required at Ashfield Park Primary School.

02/07/2026 - Award a contract to Jackwolf Group and approve the expenditure of up to £415,274 for the provision of heating works required at Ashfield Park Primary School.

Award a contract to Jackwolf Group for the heating upgrade works
required at Ashfield Park Primary School, Ross-on-Wye, Herefordshire.

Approve the expenditure of up to £370,629.90, which includes a 10%
contingency of £33,693.62 (works value is £336,936.27)

Approve the expenditure of up to £44,644.05 for external and internal
fees.

Responsibility for monitoring the programme to be carried out by the
Capital Project Manager within the spend budget.